BIAXIAL FILMS new BOPP line
Assembly, check-up and commissioning of a new 8.7m, 41,360 t/year Brückner BOPP line in Algeria, completed 2023–2025. FMS also supplied the buyer-supply steel structures back in 2018.

Overview
FMS assembled, checked and commissioned a brand-new 8.7m, 41,360 t/year Brückner BOPP line for Biaxial Films in Algeria between 2023 and 2025.
Scope
Buyer-supply steel structures, crane rails and chimney (2018)
Full assembly of the 8.7m Brückner line
Check-up and commissioning to full production
Outcome
One of the largest single-line BOPP investments in the region brought online and running.